The DIA process will commence once the developer has submitted a PPE. However; a DIA for a surface water connection could involve varying degrees of complexity depending on the size of development, the discharge rate required and the sensitivity of the proposed receiving network. The proportional change in the existing operation of the network will be a defining factor to establishing the appropriate methodology and complexity for the DIA.
Relatively small increases in predicted flow may be satisfactorily assessed using a desktop approach with some supporting manual calculations. More complex predicted impacts will require detailed analysis, up to and including hydraulic modelling.
While Anglian Water can undertake detailed analysis, our resources are limited and often committed on our investment programme. Therefore, we would encourage developers to utilise their own resources to undertake such detailed analysis that may be required, to minimise avoidable delay. Analysis completed by the developer can be submitted to Anglian Water for review and approval.
Site specific details will influence the selection of the assessment method, so a pre-application consultation with our DS Growth Planning team is recommended to ensure the correct information is submitted at PPE.
In general, the process would be expected to progress in the following steps:
i. Pre-application to confirm relevant information
ii. PPE to provide the developer with sewer network asset data, necessary to represent existing capacity
iii. Developer incorporates sewer network data into the SW design hydraulic calculations
iv. Developer submits hydraulic calculations to Anglian Water for checking and approval
If required….
v. Developer submits outline proposals for mitigating predicted impact or network reinforcement
vi. Anglian Water will consult with its operational teams and specialists on the viability of proposed mitigation measures
vii. Developer funds network reinforcement under the appropriate section of WIA1991